Most buyers spend three months choosing a paper cup machine and three days planning what happens when it arrives. Then the crate lands, the forklift is booked for one hour, and everyone discovers at the same moment that the workshop door is 20 cm too narrow.
The machine is the easy part. The first 30 days decide whether you run at the promised speed or spend a year blaming the supplier for a problem that was created before the machine was unpacked. This is the sequence we follow when we commission a line — and the five points where installations usually go wrong.
The machine cannot be installed into a building that is not ready for it. Each of these five items has a lead time longer than the machine's own production lead time, which is why they are always the bottleneck.
A forming machine rated at 13, 20 or 22 kW (our XC-100, XC-130s / XC-116 and XC-150s respectively) is only part of the connected load. A realistic single-line installation adds:
| Load | Typical | Supply |
|---|---|---|
| Forming machine | 13–22 kW | 380 V, 3-phase |
| Air compressor | 4–7.5 kW | 380 V, 3-phase |
| Refrigerated air dryer | 0.3–0.6 kW | 220 V |
| Packing machine (XC-800) | ~1 kW | 220 V single-phase |
| Lighting, air conditioning, office | 3–8 kW | 220 V |
| Example total | ~32 kW ≈ 40 kVA | main breaker ~63 A at 380 V |
Four things to settle with your electrician before the machine ships:
Each forming machine needs 0.4 m³/min at 0.4–0.8 MPa, and it needs it dry. Water in the air line shows up as sealing faults, sticky solenoid valves and rust in cylinders — usually three months later, when nobody connects it to the cause.
Cup machines weigh 2,400–2,900 kg; bowl machines up to 4,200 kg. Most do not need a special foundation, but they do need:
Cup board is a hygroscopic material. The same machine, the same moulds and the same operator produce different rejects in a humid month. Aim for:
The best predictor of a smooth start is not the machine. It is whether one named person owns the line — start-up, quality checks, fault log, spare parts. Split responsibility between three managers and the first month disappears into meetings.
Commissioning is a sequence. Skipping a step moves the problem rather than removing it.
A demonstration is not a test. The acceptance test is your only chance to measure the machine while the supplier's engineer is still standing next to it, so define the numbers before the crate ships.
| Check | Method | Pass criterion |
|---|---|---|
| Measured speed | Count sellable cups over 2 hours at steady state | ≥85% of rated for that cup size, or the figure in your contract |
| Reject rate | Classify every reject over the same 2 hours | ≤3% on a standard cup at commissioning |
| Rim diameter and height | Caliper or go/no-go gauge, 20 cups | Within the drawing tolerance |
| Seam strength | Peel test on 20 cups | Fibre tear, not a clean peel |
| Bottom seal | Fill 20 cups with water at 90–95 °C, stand 2 hours | No wicking or softening at the seal |
| Stack height | 50-cup stack | Within your filling line's specification |
| Print registration | If printed | ±1 mm |
| Mould change | Time it, two people | Under 60 minutes |
| Noise and vibration | Full speed, all stations | No abnormal sound or movement |
Run the test for at least four hours, and include a mould change if you bought more than one set. A machine that passes clean but fails after a changeover has a setup problem you will live with for years.
Handing over on day one is how factories end up with a machine that only runs well when the supplier's engineer visits.
Operators need to know: start/stop and safe shutdown, recipe loading, clearing a jam without damaging the moulds, the 30-minute quality check, and how to log a reject.
The mechanic needs to know: mould change, seal and heater replacement, lubrication points, belt tension, and what must never be adjusted without a record.
The supervisor needs to know: how to read the reject log, how to receive board (batch, moisture, certificate), and how to calculate OEE — availability × performance × quality.
Run supervised production for 3–5 days, then two further weeks with daily checks. Expect the reject rate to fall from 3–8% in the first weeks to 2–4% by the end of the first month. On a 122,000-cup day, a five-point reject rate is 6,000 cups of board, coating and power going into a bin.
Almost every early fault is one of eight things. Learn these and you will diagnose most problems before you call anyone.
| Symptom | Most likely cause | Check first |
|---|---|---|
| Bottom leak | Seal temperature or pressure low; board too dry or too damp; bottom disc misaligned | Actual vs set temperature; board moisture; bottom alignment |
| Side seam leak | Seam temperature or dwell; coating batch variation; worn seam guide | Seam temperature; new paper batch; seam width |
| Rim crack | Board too stiff for the rim; curl too tight; board too dry | Board grade against specification; moisture; curl setting |
| Jams at the feed | Humid board; worn feed rollers; low air pressure; static | Air pressure; board acclimatisation; roller condition |
| Scorching or smell | Temperature too high; dwell too long; thermocouple drift | Contact-thermometer check; heating time |
| Off-size cups | Mould wear; machine out of level; speed too high | Mould condition; level; speed |
| Count errors | Dusty sensor; reflective print | Sensor lens; sensor type |
| Seam opens in the customer's hand | Under-sealed; board too thick for the settings | Peel test on retained samples |
The rule is simple: change one variable at a time, and write down what you changed. Most "machine problems" in the first month are paper problems, temperature problems, or settings that were never recorded.
| Frequency | Tasks |
|---|---|
| Daily | Clean the forming area; drain the air tank and filter; check oil; check temperature actual vs set; log rejects |
| Weekly | Clean heaters and reflectors; check belt tension; lubricate per manual; inspect seals and rollers; check for air leaks |
| Monthly | Inspect cams and bearings; verify thermocouples; clean the electrical cabinet; test safety interlocks; inspect moulds |
| Quarterly | Gearbox oil; motor insulation; re-check alignment; review spare-parts stock |
Stock these from day one: heater elements, thermocouples, sealing dies, feed rollers, belts, bearings, proximity sensors, solenoid valves, a PLC battery, fuses, mould screws, air filter elements and oil. A machine stopped for three weeks by a low-cost heater is a planning failure, not a machine failure.
Keep a downtime log — time, symptom, cause, fix, minutes lost — from the first shift. After a year it is the most valuable document in the factory, because it tells you what to prevent instead of what to repair.
Commissioning is the end of one decision chain and the start of another. If you are still upstream of the machine:
On a line we supply, the standard commissioning scope includes installation supervision, the acceptance test report, operator and mechanic training, a recorded parameter card for each mould set, a spare-parts list with part numbers, and remote support after handover. Send us your site details — supply, air, floor, ambient conditions — and we will send the preparation checklist before the machine ships.
How long does installation and commissioning take?
Typically 3–7 days for a single forming line, depending on the number of mould sets and how ready the site is. Plan on 2–4 weeks of supervised production after handover before you consider the line stable.
Do I need a special foundation?
Usually not. A level, load-bearing concrete floor is enough for a 2,400–2,900 kg cup machine; anchor bolts or vibration pads are fitted at commissioning. If your building is suspended or the slab is thin, have a structural engineer check it before delivery.
What power supply do I need?
380 V three-phase 50 Hz is the standard build; 220 V / 60 Hz and other builds are available. Size the supply for the forming machine plus compressor, dryer, packing and building load — around 40 kVA for the single-line example above.
What compressor should I buy?
One that delivers at least 0.4 m³/min at 0.6–0.8 MPa per forming machine, with a refrigerated dryer and a receiver tank. A bigger tank is cheaper than a bigger compressor for this duty cycle.
How many people does one line need?
One operator per forming machine per shift, plus one or two people on packing and inspection. A mechanic can cover several lines.
What spare parts should I stock before the first month ends?
The list in section 7: heaters, thermocouples, seals, rollers, belts, bearings, sensors, solenoid valves, PLC battery and fuses.